Description of the risk and methods used to manage it

The main risk is the delay of raw materials caused by severe weather, which might influence procurement, production, and transportation departments. Based on CSC's assessment, without adaptation measures, the financial impact could be less than 0.5% of CSC's revenue

As country of origin of some raw materials are covered by high physical risk (such as floods), CSC has implemented several adaptation measures, with total investments accounting for approximately 0.6% of CSC's CAPEX :

Result: Reducing the transport cycle from 60 days to 3 days, which will solve the problem of uncontrollable factors affecting the material use of the long distance.