Date Chronicle of Events
 The Turnkey Project First Phase of Danhai Light Rail Transit
2014.11.07 After the Procurement selection meeting, CSC was selected as the most favorable bidder.
2014.11.23 Notice to Proceed (NTP).
2014.12.05 Contract Signing Ceremony.
2016.11.09 The 1st tram delivery for test.
2017.11.30 Green Mountain Line Connecting Ceremony.
2018.12.10 The final inspection of Green Mountain Line (V01 Hongshulin Station to V11 Kanding Station) was completed by the Ministry of Transportation and Communications.
2018.12.24 The Green Mountain Line (V01 Hongshulin Station to V11 Kanding Station) started service officially.
2019.09.19 CSC was honored with the Public Construction Quality Award, the Public Construction Assessment Quality Award, and the First Prize in the Public Construction Quality Award - Special Jury Award in the public construction category by the Formosa Association of Sustainable Care for Living Environment during the 20th National Golden Award for Architecture in 2019.
2019.11.23 CSC received the 2019 Digital Construction Innovation Application Award and the 2019 Construction Environment and Beautification Award in the construction beautification and landscaping category from the Chinese Institute of Civil and Hydraulic Engineering.
2020.07.24 CSC was honored with the Golden Quality Award and the Excellence Award in the public art category by the Real Estate Association of the Republic of China during the FIABCI - Taiwan Real Estate Excellence Awards 2020.
2020.08.07 CSC received the 2020 Construction Excellence Award from the Chinese Institute of Engineers.
2020.10.16 Blue Seaside line and depot passed the second review of Ministry of Transportation and Communication.
2020.11.09 The construction of maintenance depots, rail tracks, other facilities, and electrical systems were completed.
2020.11.15 Blue Seaside line commenced the operation.
2020.12.03 CSC was honored with the Public Construction Quality Award, the Public Construction Assessment Quality Award, and the First Prize in the Public Construction Quality Award - Special Jury Award for the public construction category by the Formosa Association of Sustainable Care for Living Environment during the 21st National Golden Award for Architecture in 2020.
2020.12.15 RAMS commenced on the start date of RSD as trial operation began.
2021.06.11 The E&M systems for the Danhai Light Rail Transit Project was officially completed after successfully passing the overall review of RAMS.
2021.11.10 CSC won the 2021 Public Construction Quality Award presented by the New Taipei City Government.
2021.11.22 CSC received the 2021 Construction Excellence Award from the Chinese Institute of Engineers.
2021.11.27 CSC was honored with the 2021 Construction Environment and Beautification Award and the 2021 Excellent Construction Award in the construction beautification and landscaping category by the Chinese Institute of Civil and Hydraulic Engineering.
The Turnkey Project of Kaohsiung Circular Light Rail Transit (Phase II)
2016.08.10 After the Procurement selection meeting, CSC was selected as the most favorable bidder.
2016.09.09 Contract Signing.
2016.10.11 Notice to Proceed (NTP).
2017.02.09 Groundbreaking Ceremony.
2018.01.30 This project was selected as an excellent construction site award of Kaohsiung City in 2017.
2018.09.27 The 1st tram delivery for test.
2018.10.04 The 1st tram on-line test (C14 Hamasen Station to C17 Gushan District Office Station).
2018.12.13 This project was selected as the excellent construction site award of Kaohsiung City in 2018.
2019.04.03 CSC reached a new milestone in the Kaohsiung Light Rail Transit Project after “substantial completion of systems between Stations C14 (excluded) and C17 to the extent that they can be delivered to the operator for preliminary and final inspections” (NTP+900 days).
2019.11.25 The Turnkey Project of Kaohsiung Circular Light Rail Transit (Phase II)-C32~ C37~C1 (excluding C1 station) was selected as an excellent construction site of Kaohsiung City in 2019.
2020.11.20 CSC won the 2020 Urban Construction Golden Quality Award for the construction of “Station C37 and pedestrian bridge” and the production of “light rail rolling stock.”
2021.01.12 The Great Southern Ring (C32-C37-C1-C17) in Phase 2 of the Kaohsiung Light Rail Transit Project began trial operation.
2021.09.11 CSC won the 2021 Urban Construction Golden Quality Award won the construction of “Station C18 and pedestrian bridge” and “light rail vehicles.”
2021.12.16 Stations C17 to C20 of Kaohsiung Light Rail Transit began trial operation.
2022.10.05 Trial operation of section C20-C24
The Turnkey Project of Ankeng Light Rail Transit-Mechatronics Engineering
2016.06.01 The Performance Review Committee evaluated that CSC is a certified manufacturer and according to the regulations, the proprietor can sign up for the project procurement for this object.
2016.09.27 Successfully completed the price negotiation with the proprietor.
2016.11.11 Contract Signing.
2017.04.26 Contract signing ceremony with Taiwan Rolling Stock Co., LTD (TRSC).
2017.05.01 Notice to Proceed (NTP).
2018.10.22 Final design proposal completed.
2019.12.26 CSC was ranked No. 1 in the Performance Evaluation of Turnkey Contractors for the First Half of 2019 by the Department of Rapid Transit Systems, New Taipei City.
2021.02.04 CSC was ranked No. 1 in the Performance Evaluation of Turnkey Contractors for 2020 by the Department of Rapid Transit Systems, New Taipei City.
2021.09.30 The first set of rolling stock arrived at Ankeng Depot.
2021.12.28 CSC was ranked No. 1 (Excellent) in the Performance Evaluation of Construction Contractors for 2021 by the Department of Rapid Transit Systems, New Taipei City.
2022.08.19 Included in New Taipei City Government's list of companies with excellent public construction performance (award of excellence)
2022.10.05 Trial operation of section C20-C24
2022.12.11 Completed the preliminary survey